Gyeongbu Expressway: Completing the Daejeon-Daegu Section
The Gyeongbu Expressway was built to address transportation shortages caused by industrialization. Funded mainly from domestic sources, it was completed on June 30, 1970, following final work on the Daejeon-Daegu section. The entire route opened on July 7 that year.
- Transportation shortages, which worsened from 1965, arose because transport capacity failed to keep pace with economic growth and rising production.
- Various financing options, including foreign capital, were considered, but domestic funding covered almost all actual construction costs.
- The Daejeon-Daegu section was particularly challenging because it involved both bridge construction across the Geum River and tunnel construction through mountainous terrain.
- The entire route was completed on June 30, 1970, and opened on July 7 of the same year.
- Kim Won-gi's prediction that the expressway would reduce regional disparities must be distinguished from empirically demonstrated results after its opening.
The Gyeongbu Expressway was built to address transport shortages caused by industrialization. After construction began in 1968, the project overcame funding shortages and difficult work between Daejeon and Daegu. With domestic funding secured and construction carried out by section, it was completed in 1970 and is remembered as a turning point in the transport network supporting industrialization.
This article follows the National Archives of Korea’s records on the Gyeongbu Expressway and was checked as of October 2026.
Background to the Construction of the Gyeongbu Expressway
Construction was prompted by transport capacity that could not keep pace with rising production. The First Economic Development Plan also pursued the restoration and expansion of transport facilities. However, the National Archives of Korea explains that transport shortages worsened from 1965. Transport capacity could not keep up with the growing economy. National Archives of Korea’s explanation of the construction background
The expressway plan took shape alongside national land development policy. The Comprehensive National Land Construction Planning Act was enacted in 1963. The 1967 “Grand National Land Construction Plan (Draft)” included expressway construction. The Gyeongbu route was intended to connect major cities and centers of production and consumption.
Timeline of Construction, Completion, and Opening
The start of construction marks the beginning of the work, while completion means the work is finished. Opening is the stage when the completed road is made available to traffic. Completed sections of the Gyeongbu Expressway opened before the rest. The opening dates of individual sections therefore differ from the opening date of the entire route.
| Date | Event | Source |
|---|---|---|
| April 29, 1967 | President Park Chung-hee announced a plan to build an expressway between Seoul and Busan | Kim Won-gi, “The Significance of the Opening of the Gyeongbu Expressway” |
| December 15, 1967 | A survey team for the national trunk expressway construction plan was established | Project overview in the same article |
| February 1, 1968 | The project began with construction of the Seoul to Suwon section | Schedule in the same article |
| December 21, 1968 | The Seoul to Suwon section opened | Schedule in the same article |
| December 30, 1968 | The Suwon to Osan section opened | Schedule in the same article |
| September 29, 1969 | The Osan to Cheonan section opened | Schedule in the same article |
| December 10, 1969 | The Cheonan to Daejeon section opened | Schedule in the same article |
| December 29, 1969 | The Daegu to Busan section opened | Schedule in the same article |
| June 27, 1970 | Paving of the approaches to Dangjae Tunnel was completed | National Archives of Korea’s explanation of the Daejeon construction section |
| June 30, 1970 | The entire route was completed with the completion of the Daejeon to Daegu section | Schedule in Kim Won-gi’s article |
| July 7, 1970 | The entire route opened | National Archives of Korea’s Records of the Month for July 2014 |
Kim Won-gi’s article was written by the vice minister of construction at the time. The project schedule was compiled from its project overview and schedule. The date of the finishing work on Dangjae Tunnel was supplemented by the National Archives of Korea’s explanations of individual construction sections. Original article by Kim Won-gi, Explanation of the Daejeon construction section
Construction Costs and Funding
Domestic funding covered almost all actual construction costs. Borrowing money from abroad was also considered early on. However, difficulties in securing foreign capital coincided with the suspension of loan plans. Not every funding option considered should be read as having actually been used. National Archives of Korea’s explanation of funding
| Category | What the records show | Distinction to keep in mind |
|---|---|---|
| Foreign funding considered | Equipment and materials loans, grain loans | Consideration does not mean borrowing actually occurred |
| Domestic funding considered | Fuel tax increases, public bonds, tolls, military support, and other sources | The list of options alone does not show how much each source contributed |
| Actual funding outcome | Domestic funding covered almost all construction costs | This should not be overstated as entirely domestic funding |
Construction costs also changed from the planning stage. The original budget set after review was 33 billion won. In March 1969, the Ministry of Construction requested 42.973 billion won. The additional amount requested was 9.973 billion won.
Kim Won-gi recorded total construction costs of 42.973 billion won for the project completed in 1970. This amount is stated in the monetary value of the time. Comparing it with construction costs today requires separate adjustments for prices and the scope of work. Revisions to project costs
The Difficult Daejeon to Daegu Section of the Gyeongbu Expressway
The Daejeon to Daegu section required bridge and tunnel construction to proceed together. A difficult construction section is one where terrain and construction conditions make the work challenging. Finishing work in the Okcheon and Yeongdong areas remained a particular problem. Construction status documents from the time also confirm the difficulties in these areas. Explanation of “Construction Status of the Seoul to Busan Expressway”
The National Archives of Korea identifies the stretch between Usan-ri and Myogeum-ri in Okcheon as a particularly difficult section. A bridge had to be built across the Geumgang River. A tunnel through Dangjae also had to be built in the same section. This meant that completing the roadbed alone would not make the road passable. Terrain and construction in the Daejeon construction section
| Construction condition | Work required | Effect on completion |
|---|---|---|
| A route crossing the Geumgang River | Construction of a bridge across the river | Roads on both sides of the river needed to be connected |
| A route passing through Dangjae | Construction of a tunnel through the mountain | Vehicles could pass only once the tunnel was completed |
| Connections between bridges, tunnels, and ordinary road sections | Paving of approaches and roads | Finishing work was still needed after the structures were completed |
The 1970 construction status document reports that the bridges had been completed. Dangjae Tunnel, however, remained a structure where progress was slow. This shows where the bottleneck lay in the final stages of construction. The document alone, however, cannot establish the effectiveness of any particular construction method.
Why Paving the Approaches to Dangjae Tunnel Was a Turning Point
The finishing work on Dangjae Tunnel marked a turning point by connecting a route that had remained broken. The National Archives of Korea explains that paving of the approaches was finished on June 27, 1970. The entire route was then completed on the 30th of the same month. This is why the completion of tunnel work must be distinguished from the completion of the overall project. Completion records for the Daejeon construction section
Road formation work on the Daejeon to Daegu section was finished by the end of 1969. Work on structures such as tunnels and long-span bridges, along with paving, continued into the following year. This sequence shows that cutting and filling earth alone does not complete a road. Kim Won-gi’s project overview
Results of the Gyeongbu Expressway’s Opening and Loss of Life
On July 7, 1970, the entire route connecting Seoul and Busan opened. The route built at the time was 428km long, with four lanes in total for both directions. These figures describe the scale of the project when it was completed in 1970. They do not describe the length or lane count of the current route. National Film Production Center, “The Road to Prosperity”
Later commentary by the National Archives of Korea assesses the expressway network’s economic role. That assessment also covers increased exchange between regions and the expansion of areas accessible within a day. The network was subsequently expanded to include routes such as Honam, Namhae, and Yeongdong. However, the full effects of the later network cannot be attributed to the Gyeongbu route alone. National Archives of Korea’s July 2014 commentary
Lives were also lost during construction. The National Museum of Korean Contemporary History states that 77 people died in the course of the work. A memorial tower was erected near Geumgang Service Area to honor them. The construction period and costs alone cannot account for the project’s human toll. National Museum of Korean Contemporary History’s record of the memorial tower
Records and Interpretation
The expectations of officials at the time must be distinguished from measurements of results after the opening. Kim Won-gi’s article is an account by a government official who helped carry out the project. Alongside the construction schedule, it includes assessments emphasizing the project’s justification. Each statement should be read with attention to the nature of the record.
Second, the opening of the expressway eliminates regional disparities.
Kim Won-gi, “The Significance of the Opening of the Gyeongbu Expressway,” Local Administration 19-201, 1970, Social Significance. Original text held by the National Archives of Korea
This sentence shows the regional development effects the government expected at the time. It is not itself statistical evidence of reduced regional disparities. Assessing the actual effects requires regional data from before and after the opening. Changes in income, population, and factory locations must also be examined.
| Category | What can be stated | Limits of the assessment |
|---|---|---|
| Contemporary records | Construction schedules, project costs, and government officials’ expectations | The writer’s assessment must not be treated as an outcome |
| Later institutional interpretations | An assessment of the road as a transport network supporting industrialization and interregional exchange | Institutional commentary cannot be treated as a consensus among all historians |
| Issues requiring separate verification | The extent to which regional disparities were reduced and the effects of concentrating investment along the Gyeongbu corridor | Long-term regional statistics and comparisons of research are needed |
Standards for Citing Tunnel Counts and Lengths
Figures for the same facilities can differ depending on the unit of counting. Kim Won-gi’s project overview lists six tunnel sites. The National Archives of Korea’s explanation counts 12 tunnels by separating the two directions of travel. When quoting a number, it is therefore necessary to state what was counted. National Archives of Korea’s tunnel statistics
| Type of figure | Basis that must be stated | Confusion to avoid |
|---|---|---|
| Tunnel count | Whether the count refers to tunnel sites or separate tunnels for each direction | Comparing six sites and 12 tunnels as if they used the same unit |
| Route length | Whether it refers to the route as built or the route after later changes | Using the 1970 figure of 428km as the current length |
| Project costs | Whether the figure is the original budget, a revised amount, or the cost at completion | Treating amounts from different stages as equivalent |
| Construction dates | Whether the date marks completion of a structure, completion of the entire route, or opening | Using June 27, June 30, and July 7 interchangeably |
Length figures also require checking what the original source included in its totals. The tunnel statistics page contains some entries whose lengths differ between the body text and the table. This article has not arbitrarily corrected those differences. Precise comparisons of lengths require checking the original tables from the construction history reproduced there.
Lasting Significance for Understanding Today’s Transport Network
This case shows the continuing process of connecting and expanding a transport network. Lane widening and alignment improvements continued after the entire route opened. The National Archives of Korea presents the history of widening on sections including Cheongwon to Hoedeok and Hoedeok to Jeungyak. Completion in 1970 was also the starting point for later road improvements. The Daejeon construction section and its later widening history
Assessing the project at the time also requires separating the questions. Construction records can establish whether the transport corridor was connected. Assessing the size of the economic gains requires traffic volume and cost data. Which regions received the benefits is a matter for separate regional analysis.
Frequently Asked Questions
Why do the completion date and the opening date of the entire route differ?
Completion means the construction work is finished, while opening means the road is made available to traffic. The entire route was completed on June 30, 1970. Its opening was recorded as July 7 of the same year.
Was the entire Daejeon to Daegu section equally difficult?
The records point in particular to difficulties in the Okcheon and Yeongdong areas. Around Dangjae, bridge and tunnel construction proceeded together. The entire section should not be described as having the same terrain or construction conditions.
Was it built with money borrowed from abroad?
Foreign funding was one of the options considered. The National Archives of Korea explains that domestic funding covered almost all actual construction costs. Not every loan considered should be counted as funding actually obtained.
Can the opening be said to have eliminated regional disparities?
An official’s article from the time is not enough to establish that conclusion. Kim Won-gi’s sentence shows the effects the government expected. Actual changes in regional disparities must be assessed through statistics and research from after the opening.
FAQ
Why was the Gyeongbu Expressway built?
Because transport capacity became insufficient as the economy and production grew. The National Archives of Korea explains that transport shortages worsened starting in 1965.
When did construction start, when was it completed, and when did the entire route open?
Construction started on February 1, 1968. Construction of the entire route was completed on June 30, 1970. The entire route opened on July 7 of the same year.
Were some sections available for use before 1970?
Sections opened as they were completed. The Seoul-Suwon section opened on December 21, 1968. The Daegu-Busan section opened on December 29, 1969.
Why was the Daejeon-Daegu section difficult to build?
Because it involved both bridge construction across the Geumgang River and tunnel construction through mountainous terrain. Construction status records from the time identify the Okcheon and Yeongdong areas as difficult sections.
When was Dangjae Tunnel finished?
The National Archives of Korea explains that paving of the approaches was completed on June 27, 1970. This date is distinct from June 30 of the same month, when construction of the entire route was completed.
What was the total construction cost?
The total construction cost of the project completed in 1970 was recorded as 42.973 billion won. This must be distinguished from the original budget of 33 billion won.
Was construction funded entirely from domestic sources?
The National Archives of Korea explains that domestic funding accounted for almost all of the construction cost. This should not be taken to mean that the project was funded entirely from domestic sources.
How should the record of 6 tunnel locations and the description of 12 tunnels be interpreted?
The number of tunnel sections must be distinguished from the number of tunnels counted separately for each direction of travel. The National Archives of Korea's explanation of the tunnels gives a count of 12 when tunnels are counted separately by direction.
How many people were recorded as having died in the line of duty during construction?
The National Museum of Korean Contemporary History states that 77 people died in the line of duty during construction. The memorial tower near the Geumgang Service Area was built to honor them.
Does Kim Won-gi's claim about reducing regional disparities refer to actual results?
That statement was a forecast presented by a government official at the time of opening. How much regional disparities decreased must be verified separately using subsequent regional statistics and research.
Sources
- National Archives of Korea, Construction of the Gyeongbu Expressway, the Nation's Main Artery: Planning the Route
- National Archives of Korea, Gyeongbu Expressway Construction Funding and Project Cost Statistics
- Kim Won-gi, The Significance of the Opening of the Gyeongbu Expressway, Local Administration 19-201, 1970
- National Archives of Korea, Records of the Month for July 2014: Expressways, Linking the Nation's Main Arteries
- National Archives of Korea, Seoul-Busan Expressway Construction Status, No. 179, 1970, BA0139280
- National Archives of Korea, Building the Road: Daejeon Construction Section
- National Archives of Korea, Gyeongbu Expressway Tunnel Statistics
- National Archives of Korea, National Film Production Center Cultural Film Road to Prosperity, 1970
- National Museum of Korean Contemporary History, Modern and Contemporary History Archive, Gyeongbu Expressway Memorial Tower for Those Who Died in the Line of Duty